CASE STUDY 1
CLIENT:

F******Y

BENGALURU

3,50,000 Sq.Ft

SCOPE:

Interior Fit-out Management

Quality, Safety & Timelines

Design & Procurement Coordination

45 Days 

Phase-1 completion

120 Days 

Total project completion

0 Days 

Loss of Time

20 % 

Savings over budgeted costs

HOW DID WE ACHIEVE:

 

  • A thorough risk assessment was undertaken prior to the start of the project

  • A meticulous schedule was prepared for the phase-1 requirements with vendor inputs

  • A detailed resource allocation along with a precise cash-flow statement was prepared and agreed upon

  • Contractor selection was made based on track-record in delivering fast-track high quality projects

  • A cash incentive scheme was worked out to reward vendor partners for speedy and high-quality outcomes

  • Close coordination with Finance teams to ensure Times payments and unhindered work progress

  • On-site Design coordination team ensured quick clearances of design specs for seamless job progress

  • Strategic sourcing  logistics partner ensured just-in-time deliveries

  • Simple and quick Handing over documentation ensured timely taking over formalities

CASE STUDY 2

CLIENT:

G***********S

BENGALURU

2,00,000 Sq.Ft

SCOPE:

Interior Fit-out Management

Quality, Safety & Timelines

Design & Procurement Coordination

45 Days 

Phase-1 completion

90 Days 

Total project completion

0 Days 

Loss of Time

30 % 

Savings over budgeted costs

HOW DID WE ACHIEVE:

  • A thorough risk assessment was undertaken prior to the start of the project

  • A meticulous schedule was prepared for the phase-1 requirements with vendor inputs

  • A detailed resource allocation along with a precise cash-flow statement was prepared and agreed upon

  • Contractor selection was made based on track-record in delivering fast-track high quality projects

  • A cash incentive scheme was worked out to reward vendor partners for speedy and high-quality outcomes

  • Close coordination with Finance teams to ensure Times payments and unhindered work progress

  • Dedicated Design coordinator on site ensured quick clearances of design specs

  • Prioritizing local/regional sourcing and rail logistics ensured quick deliveries

  • Simple and quick Handing over documentation ensured timely taking over formalities